Millport Ave and Olmstead Court Main Replacement - New Canaan

May 9, 2022 Connecticut

Project Goals and Objectives

A water main replacement project is scheduled to begin in May on Millport Avenue and Olmstead Court and is expected to be completed by in June. Final paving will then be scheduled in coordination with the Town of New Canaan.

Scope of Work

The project, which will replace approximately 1,300 feet of water main, is part of an ongoing program to improve Aquarion’s water distribution system and to ensure the highest quality water. The upgrades will also help to reduce leaks and water main breaks that can cause service interruptions. Due to construction, customers should expect minor traffic delays and possible detours during the working hours of 7:00 a.m. to 5:00 p.m. 

overhead map of Millport Ave and Olmstead Court project limits

 

Schedule

  • Construction begins May 2022
  • Construction completion in June 2022
  • Restoration and final paving will follow in coordination with the Town of New Canaan

Contacts

  • Contractor:  A J Penna & Son Construction, Inc, John Torielli, (914) 999-0688
  • Engineer/Inspector: Snyder Civil Engineeing, Jim Dabbo, 860-342-1370
  • Aquarion Project Manager: Nicholas Monelli, (203) 257-7443