Quintard Place Main Replacement - Westport

Apr 27, 2022 Connecticut

Project Goals and Objectives

A water main replacement project is scheduled to begin in April on Quintard Place. Construction will be complete by May 15th and final restoration should be completed by July 1.

Scope of Work

The project, which will replace approximately 700 feet of water main, beginning at Maple Avenue South and ending in the cul-de-sac on Quintard Place. This is part of an ongoing program to improve Aquarion’s water distribution system and to ensure the highest quality water. The upgrades will also help to reduce leaks and water main breaks that can cause service interruptions. Due to construction, customers should expect minor traffic delays and possible detours during the working hours of 7:00 a.m. to 5:00 p.m. 

overhead map of Quintard Place project limits

 

Schedule

  • Construction begins April 2022
  • Construction completion by May 15, 2022
  • Final restoration should be completed by July 1, 2022

Project Contacts

  • Contractor: AJ Penna Construction, (203) 846-1577
  • Engineer/Inspector: Luchs Engineering, (203) 379-0320
  • Aquarion Project Manager: Art Bradshaw, (203) 337-5851