North Main Street Main Extension - Marlborough

Sep 21, 2021 Connecticut

Project Goals and Objectives

A new water main extension project is scheduled to begin early October on North Main Street and between Keirstead Circle and Sherwood Lane. Work is expected to be completed by the end of November. Final paving will then be scheduled and performed by the Town of Marlborough in the spring of 2022. 

Scope of Work

The project, which incorporates approximately 2819 feet of water main, is part of an ongoing program to improve Aquarion’s water distribution system and to ensure the highest quality water. During construction, customers should expect minor traffic delays and possible detours during the working hours of 7:00 a.m. to 5:00 p.m.

overhead map of Marlborough St. Project Limits

Schedule

  • Construction to begin early October
  • Completion by end of November
  • Restoration and final paving will be scheduled in coordination with the Town of Marlborough in the spring of 2022.

Contacts

  • Contractor:  D&G Contractors, Kevin Plourde, (860) 747-5834
  • Engineer: Weston and Sampson, Robert Colantonio, (860) 867-6427
  • Aquarion Project Manager: Phat Phung, (203) 337-5957