Squadron Line Rd, Eagle Ln, Gretel Ln, Weatherly Rd & Ox Yoke Dr Main Replacement - Simsbury

Sep 13, 2021 Connecticut

Project Goals and Objectives

A water main replacement project is scheduled to begin July 19th for Squadron Line Rd, Eagle Ln, Gretel Ln, Weatherly Rd and Ox Yoke Dr. Work is expected to be completed by end of October.   Final paving will then be scheduled in coordination with the Town of Simsbury.

Scope of Work

The project, which will replace approximately 8820 feet of water main, is part of an ongoing program to improve Aquarion’s water distribution system and to ensure the highest quality water.  The upgrades will also help to reduce leaks and water main breaks that can cause service interruptions. Due to construction, customers should expect minor traffic delays and possible detours during the working hours of 7:00 a.m. to 5:00 p.m. 

overhead map of Simsbury, Connecticut project limits

Schedule

  • Construction to begin July 19th
  • Completion by end of October
  • Restoration and final paving will be scheduled in coordination with the Town of Simsbury

Contacts

  • Contractor:  Simscroft Construction, (860) 651-0231
  • Engineer: Sargis Associates, (860) 461-1544
  • Aquarion Project Manager: Mark McCaffrey, (203) 362-3070