Anderson Road and West Brother Drive Main Replacement - Greenwich

Sep 10, 2021 Connecticut

Project Goals and Objectives

A water main replacement project is scheduled to begin on May 24th on Anderson Road and West Brother Drive, from Woodside Drive to Mallard Drive. Work is expected to be completed by the end of August. Final paving will then be scheduled in coordination with the Town of Greenwich.

Scope of Work

The project, which will replace approximately 2300 feet of water main, is part of an ongoing program to improve Aquarion’s water distribution system and to ensure the highest quality water. The upgrades will also help to reduce leaks and water main breaks that can cause service interruptions. Due to construction, customers should expect minor traffic delays and possible detours during the working hours of 7:00 a.m. to 5:00 p.m.

satellite map of Anderson Rd

Schedule

  • Construction to begin May 24, 2021
  • Completion by the end of August
  • Restoration and final paving will follow in coordination with the Town of Greenwich
  • Note: Construction will be occurring at the Mallard Road and Anderson Road intersection on July 27, 2021. Residents are encouraged to seek alternate routes if possible.

Contacts

  • Contractor: M. Rondano Construction, (203) 846-1577
  • Engineer/Inspector: Snyder Civil Engineering, (203) 342-1370
  • Aquarion Project Manager: Brenden Fimian, (203) 362-3061