Greenwich/Stamford Pipeline Replacement Project

May 20, 2020 Connecticut

Project Goals and Objectives

The project is part of an ongoing program to improve Aquarion’s water supply system.  The infrastructure upgrades will also help to reduce leaks and improve the transfer of water from the Bargh Reservoir to Rockwood Reservoir. 

Scope of Work

Aquarion will replace an existing 20-inch raw water pipeline between Bargh Reservoir Dam in Stamford and the Rockwood Lake watershed in Greenwich.

Schedule

Work is scheduled to begin May 26 on Taconic Road in Greenwich, followed by Farms Road in Stamford, and is expected to be completed by November 2020. 

Current Status

Work is scheduled to begin Tuesday, May 26.


Last update: May 20, 2020