Project Goals and Objectives

The project goal is to replace aging water mains to reduce leaks and the probability of main breaks.

Scope of Work

Replace 580 feet of water main, on Pleasant Street in Mystic, CT.

Schedule

The project is scheduled to begin on April 1, and the upgrade is expected to be completed in four weeks. Due to construction, customers should expect minor traffic delays and possible detours during the working hours of 7:00 a.m. to 5:00 p.m.