Mill Road Water Main Replacement

Mar 16, 2020 New Hampshire

Project Goals and Objectives

Replace aging water mains to reduce leaks and the probability of main breaks.

Scope of Work

Replace approximately 4,200 feet of water main between Anns Lane and Reddington Landing. The existing main is more than 60 years old and is of asbestos-cement material.  Pipe material of this age and material is prone to leaks.

Mill Road Main Replacement

Schedule

Construction on the section between Anns Lane and Barbour Road was completed this fall.  The remaining section between Barbour Road and the town line is projected to start in late March or early April.

Current Status

Installation of new 16-inch diameter, ductile iron pipe between Anns Lane and Barbour Road was completed and put into service on November 18.

Work on the section between Barbour Road and Reddington Landing is projected to start in late March or early April..

 

Last update:  March 16, 2020